Completed projects
Tehran Metro Q4 Station project, Line 4
Location of the project: Tehran, End of Pirozi St.
Subject of the contract: Construction of Metro Q4 station, in tunnel fans and rectifier
Employer: Tehran and suburb urban railway Co. (Metro)
Project management: Geno Consulting engineers
Supervisor organization: Tarhe Bamdad Consulting engineers
Contract price:139 million USD
Contract period: 24 Solar calendar months
Project starting Date: 15/09/2008
Project status: under construction
Mashad Azad University, Science faculty construction project
Project name: Science faculty construction project, Mashad Azad University
Location of the project: Golbahar New city
Subject of the contract: Construction of a 18000 square meters building with concrete structure until accomplishment of ceil phase
Employer: Mashad Azad Islamic University
Supervisor organization: Satrup Energy consulting engineers
Contract price: 7.6 million USD
Contract period: 3 solar calendar months
Project starting date: 23/10/2007
Project status: Under construction
Water transfer tunnel from Kohrang to Shahr-e kord project
Location of the project: west of Chelgard, Charmahal o Bakhtiari
Subject of the contract: construction of water transfer tunnel, with length of 1200 meters and diameter of 370 Cm
Employer: Isfahan zonal water Co
Supervisor organization: Band Ab consulting engineers
Contract price: 2 million USD
Contract period: 18 solar calendar months
Project starting date: 11/03/2003
Project status: finalized delivery
JAM petrochemical Co. OFF SITE project
Location of the project: Asaloyeh port- Boshehr
Subject of the contract: Underground fire extinguisher hose , industrial and domestic sewage pipe laying, road construction including embankment, sub base, base and asphalt, lay out and passage way concrete work, ditch and trench and manhole, lightening power wiring and earthing system, foundation, manufacturing and installation of garth lamp-posts, reservoirs, central workshop building.
Employer: Jam petrochemical Co
Supervising organization: Ista Guya consulting engineers
Contract price: 9 million USD
Project starting date: 15/05/2005
Project accomplishment date: 08/08/2008
Round road of TALEGHAN Dam
Location of the project: Taleghan public area (Zidasht)
Subject of the contract: construction of highland road, 34 Km
Employer: Tehran local water Co.
Supervising organization: Lar Consulting engineers
Initial price of the first contract: 7 million USD
Initial price of the second contract: 7 million USD
Contract period: 24 solar months
Project starting date: 11/03/2003
Project status: Under construction, 80% physical development
Accomplishment of Azadi stadium Metro Station project
Location of the project: south side of Tehran Azadi stadium
Subject of the contract: Accomplishment of concrete structures, brickwork, ceil, electrical and mechanical facilities, and land scaping
Employer: Tehran and suburb urban train
Supervising organization: Farayand Memari consulting engineers
Contract price: 4 million USD
Contract period: 9 solar months
Project starting date: 23/07/2007
Temporary delivery date: 20/09/2008
Penult statement price: 5 million Rials
C2 Recovery civil project of Pars petrochemical Co.
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: performance of all civil operations
Employer: Mobin petrochemical Co
Supervising organization: Mobin petrochemical Co
Contract price: 2 million USD
Contract period: 2 solar months
Project starting date: 23/10/2003
Project delivery date: 20/01/2004
Pars petrochemical Co. ethane recovery temporary utility project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: excavation of channel, welding and installation of carbon steel pipe with diameter of 72 inches, and hydrostatic operations with pressure of 10 bars, hydrostatic sand blast and embankment to 10 bars in under test
Employer: Mobin petrochemical Co.
Supervisor organization: Mobin petrochemical Co.
Contract price: 1 million USD
Contract period: 6 solar months
Project starting date: 02/11/2003
Project delivery date: 19/05/2004
Finalized statement price: 1 million USD
Part of Jam petrochemical Co. MEG unit steel lathing manufacturing project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: manufacturing of steel lathing of pipe racks
Employer: Pidak Co.
Supervising organization: Pidak Co.
Contract price: 2 million USD
Initial period of contract: 3 solar months
Starting date: 22/12/2003
delivery date: 15/03/2004
Part of Jam petrochemical Co. MEG unit steel lathing manufacturing project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: manufacturing of steel lathing of pipe racks
Employer: Pidak Co.
Supervising organization: Pidak Co.
Contract price: 2 million USD
Initial period of contract: 3 solar months
Starting date: 22/12/2003
delivery date: 15/03/2004
Part of Jam petrochemical Co. MEG unit steel lathing manufacturing project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: manufacturing of steel lathing of pipe racks
Employer: Pidak Co.
Supervising organization: Pidak Co.
Contract price: 2 million USD
Initial period of contract: 3 solar months
Starting date: 22/12/2003
delivery date: 15/03/2004
Manufacturing of steel lathing in Abadan refinery development unit
Location of the project: Abadan
Subject of the contract: Manufacturing of steel lathing
Employer: Pidak Co.
Supervising organization: Pidak Co.
Contract price: 5 million USD
Initial period of contract: 2 solar months
Starting date: 22/12/2003
Delivery date: 15/03/2004
Infrastructural construction of Jam petrochemical complex MEG project
Location of the project: Asaloyeh port, booshehr
Subject of the contract: constructin of buildings, civil operations, underground facilities
Employer: Jam petrochemical Co.
Supervising organization: Jam petrochemical Co.
Contract price: 5 million USD
Price of exact statement: 6 million USD
Contract period: 12 solar months
Project starting date: 22/12/2002
Exact delivery date: 9/08/2004
Mobin petrochemical Co. wall and fencing
Location of the project: Asaloyeh port, Boshehr
Subject of the contract: Execution of stone and concrete walls in Mobin petrochemical site
Employer: Mobin petrochemical Co.
Contract price: 1 million USD
Price of exact statement: 1.2 million USD
Contract period: 4 solar months
Project starting date: 24/07/2003
Temporary delivery date: 30/12/2004
Asaloyeh petrochemical area flood control and ward off project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: Flood control and ward off channels construction operations
Employer: Petrochemical industry development management Co.
Supervising organization: Band Ab consulting engineers
Contract price: 5 million USD
Price of the exact statement: 3 million USD
Contract period: 11 solar months
Project starting date: 4/01/2003
Temporary delivery date: 12/12/2004
Gas office building construction project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: Phase 1 ,2 and 3 of South Pars office building construction with infrastructure of 5500 square meters
Employer: South Pars Gas Complex
Supervising organization: SPGC plans Executing unit
Initial contract price: 11389 million Rials
Price of the exact statement: 2 million USD
Price of the second annexation: 1 million USD
Initial period of the contract: 15 solar months
Project starting date: 10/08/2003
Temporary delivery date: 1/11/2006
Fixed delivery date: 1/11/2007
Jam petrochemical MEG unit civil project
Location of the project: Asaloyeh port, Booshehr
Subject of the contract: Civil remainder works Of Jam petrochemical MEG unit
Employer: Farsa Shimi Co.
Supervising organization: Pidak Consulting engineers
Contract price: 3 million USD
Price of fixed statement: 3.4 million USD
Initial contract period: 8 solar months
Project starting date: 22/09/2004
Fixed delivery date: 15/08/2005